A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,

A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,
A) the project will currently finish under budget, assuming the project continues to perform in this way.
B) the project will currently finish over budget, assuming the project continues to perform in this way.
C) the project will currently finish on budget, assuming the project continues to perform in this way.
D) the project will currently finish behind schedule, assuming the project continues to perform in this way.
E) there is insufficient information to draw conclusions.