A way to improve estimates on future projects is to collect and archive data on past project estimates and actuals. Creating ___________ for estimating is a way to achieve this goal.
A) time and cost databases
B) history databases
C) estimating and forecasting databases
D) structured databases
E) Any of these alternatives are correct.