Consider the following table of activities that describes a project network. Is this network sensitive? Suppose indirect costs are $550 / day. For how many days could you crash this network and still be saving money because crash costs / day are less than the indirect costs / day that would be saved?
A) Yes, sensitive. 30 days.
B) Yes, sensitive. 25 days.
C) No, insensitive. 25 days.
D) No, insensitive. 30 days.
E) Neither sensitive nor insensitive. 35 days.