Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wasting money, by how many days could you reduce

Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wasting money, by how many days could you reduce the first activity that you would crash?
A) 0 day
B) 1 day
C) 2 days
D) 3 days
E) 4 days